Phoenix Closures
Greencastle, Indiana
Garmong Construction served as General Contractor for the remodel of an industrial manufacturing facility in Greencastle, Indiana, formerly known as the Oxford Automotive Building, from 220,000 to approximately 250,000 square-feet. Project components included four new additions to the building; removal, refurbishing and reinstallation of a 30-ton bridge crane, which spans approximately 80 feet across and approximately 40 feet tall; erection of six (6), 50 feet tall, 14 feet diameter silos which required installation of a 36 foot X 48 foot X 4 foot thick concrete pad; installation of a new rail spur; ten (10) new loading docks, along with the refurbish of two existing docks. There is also a 7,500-square-foot administrative area, which included training facilities. The entire project involved over 270,000 square-feet.